All Project Status Updates

  • Updated: 1 year 4 months ago
    The BSA field crew staff will be inspecting and videoing the sanitary and stormwater lines in the Main Street area in...

    Status Update:

    BSA has completed all cleaning and video inspection in the Main Street area.
  • Updated: 1 year 4 months ago
    In 2016 BSA staff worked with Continental Construction to complete $1,000,000 worth of sanitary system repairs and...

    Status Update:

    BSA field crew staff have completed line cleaning in the West Washington, East Washington, and Charlotte Avenue areas.
  • Updated: 1 year 4 months ago
    Needed upgrades to the plant

    Status Update:

    Phase 3 plant upgrades are going through design with our engineer, plant staff, and the Project Committee. The required ACT 537 Special Study report was approved by the City of Bradford and the Department of Environmental Protection (DEP). Currently storm