Plant Phase 3 Upgrades

-Excavation for 2 digester tanks, chlorine building and vehicle storage buildings have been completed.

-Concrete footers and floor for north digester tanks has been poured.

-work on north digester tank is continuing as weather permits.

-footers have been poured for new chlorine building, floor is scheduled to be poured next week, with additional work being scheduled as weather permits.

-Much of the Underground process piping and electrical duct banks has been completed in the digester tank, vehicle storage areas.

-Upgrades to lighting at the WWTP is moving forward, along with other improvements.

-Construction of new I.T. room at WWTP may begin shortly.

-New restrooms at WWTP are under construction.

Updated 1/10/19

Status Update (chronological): 

Phase 3 Upgrades continue into 2019. Click here for current updates.