Plant Upgrades

The phase 3 plant upgrade bids have been tentatively awarded at a construction cost of 9.2 million dollars. A request to PENNVEST for increased funding has been submitted. A tentative settlement date for the PENNVEST funding has been set for August 21st. A notice to proceed may be issued immediately thereafter. The phase 3 upgrades will include a diffused outfall under the stream, A new chlorine building and feed system, new sludge digesters, new reedbed facility for sludge management, a vehicle storage building, and plumbing, heating, lighting, roofing, doors, windows, and alarm system upgrades to the existing buildings.

Status Update: 

Phase 3 plant upgrades are going through design with our engineer, plant staff, and the Project Committee. The required ACT 537 Special Study report was approved by the City of Bradford and the Department of Environmental Protection (DEP). Currently storm

For questions or to report problems: 814-368-6254