Plant Phase 3 Upgrades

Updated: February 5, 2019 - 8:44am

-Excavation for 2 digester tanks, chlorine building and vehicle storage buildings have been completed. -Concrete footers and floor for north digester tanks has been poured. -work on north digester tank is continuing as weather permits. -footers have been poured for new chlorine building, floor is...Read more